
MCLAREN
AVONMOUTH, UK

MCLAREN
AVONMOUTH, UK
MCLAREN
AVONMOUTH, UK
Client:
Mclaren
Role:
Architectural
Civil & Structural Engineering
Location:
Avonmouth, Bristol
Project Details
The BE team are collectively working on the Civil/Structural engineering and BREEAM FOR McLaren Construction AND Equation Properties DELIVERING Plot 4 of the transformative Matrix 49 industrial scheme in Avonmouth, Bristol.
Works on Plot 4 commenced in February this year, with a forecasted programme of 66 weeks to deliver completion by April 2026.
Early works are set to include ground improvements and piling, alongside the installation of a new foul pumping station, and the programme will see the design and construction of the 596,000 sq. ft speculative warehouse unit, accompanied by office space, transport hubs, a link bridge, and a gatehouse.
Aligning with McLaren Construction’s commitment to sustainability, the scheme is aiming to achieve a BREEAM Excellent rating and will adhere to the Considerate Constructors Scheme and Smart Waste BRE standards